Vadgaon Nagarpanchayat Water Supply Scheme

Third Party Technical Audit report for the Vadgaon Maval Water Supply Scheme under Maharashtra Suvarna Jayanti Nagarothan. The project focuses on augmentation, treatment, transmission, and distribution improvements to deliver reliable water supply.

Location Map

Project location reference for Vadgaon Water Supply Scheme.

Vadgaon water supply project location map

Project Overview

  • Location: Vadgaon, Tal. Maval, Dist. Pune
  • Scheme: Vadgaon Nagarpanchayat Water Supply Scheme
  • Approval Program: Maharashtra Suvarna Jayanti Nagarothan
  • Designed Population: 29,810 (Year 2053)
  • LPCD Rate: 135 LPCD + 15% losses
  • Tender Cost: Rs. 30,83,52,077 (At Par)

Execution Team

  • Auditors: Dr. Rupa S. Dalvi and Dr. Gayatri S. Vyas (COEP Technological University)
  • Project Management Consultant: GeoSpatial Studio LLC, Pune
  • Contractor: M/s Eagle Infra India Ltd., Ulhasnagar, Thane
  • Work Order Date: 28/05/2025
  • Planned Completion: 27/10/2026
  • Time Limit: 18 months

Scope of Work

The scheme includes intake and pumping infrastructure, treatment plant upgrades, storage and distribution system enhancements, and associated support works. The audit scope includes site inspections, document review, and quality verification of completed works.

  • Intake Well (4.0m dia) at Jambhul Bandhara
  • Jack Well (8m dia) and approach bridge construction
  • Raw water pumping machinery (90 HP, 2+1)
  • Raw water rising main (DI K9 300mm, 6430m)
  • Unconventional WTP capacity 2.0 MLD and old WTP repairs
  • Solar plant installation (135 kW)
  • Pure water rising main (DI K9 150/200mm, 7830m)
  • Pure water gravity main (HDPE 110-250mm, 8130m)
  • RCC GSR 3.80 lakh liters at Deccan Hill
  • RCC ESR 1.9 lakh liters at Urse Khind
  • Distribution system and road reinstatement
  • Trial and run period of 1 year

Technical Context

The project serves a rapidly growing urban area near Pune-Mumbai highway and industrial zones. After comparison of available sources, Indrayani River was considered the economically suitable source for ultimate stage demand, and the augmentation plan is designed to align with future sewerage and service-level goals.

Project Gallery

Vadgaon site visuals and construction milestones

WhatsApp Image 2026-04-15 at 9.22.36 PM
WhatsApp Image 2026-04-15 at 9.22.37 PM (1)
WhatsApp Image 2026-04-15 at 9.22.37 PM (2)
WhatsApp Image 2026-04-15 at 9.22.37 PM (3)
WhatsApp Image 2026-04-15 at 9.22.37 PM
WhatsApp Image 2026-04-15 at 9.22.38 PM (1)
WhatsApp Image 2026-04-15 at 9.22.38 PM (2)
WhatsApp Image 2026-04-15 at 9.22.38 PM (3)
WhatsApp Image 2026-04-15 at 9.22.38 PM
WhatsApp Image 2026-04-15 at 9.22.39 PM (1)